Project Description

March 2018

Hydrographic River Survey

  • Contracted by State Government – Department of Biodiversity, Conservation & Attractions (or DPAW)
  • Geodetic GPS Survey Control – Levelling to Landgate and Water Gauge Benchmarks
  • Terrestrial Control Survey along riverbed with heavy tree canopy and poor line of sight.
  • Overall nearly 2 weeks work with 2km’s of cross section pickup on water (by canoe and 7m staff) and land contours up steep banks.
  • Our problem solving and grit in a challenging terrain and doing the job safely was highly praised from the DPAW project manager.
  • Deliverable’s were: Triangulation Model, 3D PDF, Plans showing contours and water depth, ASCII files.